Next Contractors Meeting
Monday, September 10th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)
Traffic impacts:
- USH 2/Belknap Street – Single lane closures from Mortorelli Drive to Ogden Avenue.
- Signed truck detour and alternate route available to bypass project.
Current Side Street Closures
- North Side
- Cumming Avenue
- Hammond Avenue
- Hughitt Avenue
- John Avenue
- South Side
- John Avenue
Work completed since last update:
- South Side
- Concrete Sidewalk
- Street Lighting
- North Side
- Grading and Gravel – Cumming to Grand Avenue
Anticipated work schedule for next week:
- South Side
- Continue work on the UW-Superior signs
- Landscaping
- Asphalt Paving
- North Side
- Curb and Gutter
- Concrete Sidewalk
- Finish Water Services
- Finish Storm Sewer
- Continue Grading and Gravel
- Begin work on Douglas County Sign
For additional information about the project, please visit the project website:http://projects.511wi.gov/