Next Contractors Meeting
Monday, September 11, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
* South Side Construction 4/11/17 – 7/13/17 Bidirectional on the north side.
* North Side Construction 7/14/17 – 8/28/17 Bidirectional on the south side.
* Median Construction 8/28/17 – 10/6/17 Traffic on the inside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
* South Side Construction 4/17/17 – 8/24/17 Bidirectional on the north side.
* North Side Construction 8/24/17 – 10/16/17 Bidirectional on the south side.
* Median Construction 10/17/17 – 11/17/17 Traffic in the outside lanes.
NO TURNING ONTO BELKNAP FROM TOWER!!!! Superior Police Department has been monitoring the intersection. Please obey all construction signs to avoid backups. Thank You.
Traffic impacts:
- East End traffic switch scheduled for Thursday 8/24/17. Traffic will be bidirectional on the new concrete pavement on the south side of Belknap.
- West End traffic switch scheduled for Monday 8/28/17. Traffic will be on the inside lanes to allow work outside of the new pavement.
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is an alternative detour route signed for other traffic to bypass the project.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Concrete Pavement & Curb and Gutter
- East End – Birch Avenue to Hill Avenue
- South side mainline concrete work completed.
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Concrete Sidewalk – North side
- East End – Birch Avenue to Hill Avenue
- North side removals
- Water main
Next Contractors Meeting
Monday, September 11, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level)
For additional information about the project, please visit the project website:http://projects.511wi.gov/