Next Contractors Meeting
Monday, August 21, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
* South Side Construction 4/11/17 – 7/13/17 Bidirectional on the north side.
* North Side Construction 7/14/17 – 9/1/17 Bidirectional on the south side.
* Median Construction 9/5/17 – 10/6/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
* South Side Construction 4/17/17 – 8/21/17 Bidirectional on the north side.
* North Side Construction 8/21/17 – 10/16/17 Bidirectional on the south side.
* Median Construction 10/17/17 – 11/17/17 Traffic in the outside lanes.
NO TURNING ONTO BELKNAP FROM TOWER!!!! Superior Police Department has been monitoring the intersection. Please obey all construction signs to avoid backups. Thank You.
Traffic impacts:
- August 22nd and 23rd: The electricians will be setting the new signals to flashing red as they program the new software.
- Oakes Avenue is closed during this stage.
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is an alternative detour route signed for other traffic to bypass the project.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Concrete Pavement
- East End – Birch Avenue to Hill Avenue
- Curb and Gutter
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Concrete Curb and Gutter
- Concrete Sidewalk
- Median Work
- East End – Birch Avenue to Hill Avenue
- Concrete Curb & Gutter
- Concrete Sidewalk
Next Contractors Meeting
Monday, August 21, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level)
For additional information about the project, please visit the project website:http://projects.511wi.gov/