Next Contractors Meeting

Monday, August 13th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.

Work completed since last update:

  • South Side
    • Sidewalk
  • North Side
    • Concrete Pavement – Grand Avenue to Catlin Avenue

Anticipated work schedule for next week:

  • South Side
    • Continue work on the UW-Superior signs
    • Landscaping
  • North Side
    • Curb and Gutter
    • Concrete Pavement Removals
    • Water Services
    • Storm Sewer

For additional information about the project, please visit the project website: http://projects.511wi.gov/belknap/