Next Contractors Meeting
Monday, July 10, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
* South Side Construction 4/11/17 – 7/17/17 Bidirectional on the north side.
* North Side Construction 7/18/17 – 9/1/17 Bidirectional on the south side.
* Median Construction 9/5/17 – 10/6/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
* South Side Construction 4/17/17 – 7/30/17 Bidirectional on the north side.
* North Side Construction 8/1/17 – 10/16/17 Bidirectional on the south side.
* Median Construction 10/17/17 – 11/17/17 Traffic in the outside lanes.
Banks Avenue to John Avenue (West End) Traffic Control
* South Side Construction 4/11/17 – 7/17/17 Bidirectional on the north side.
* North Side Construction 7/18/17 – 9/1/17 Bidirectional on the south side.
* Median Construction 9/5/17 – 10/6/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
* South Side Construction 4/17/17 – 7/30/17 Bidirectional on the north side.
* North Side Construction 8/1/17 – 10/16/17 Bidirectional on the south side.
* Median Construction 10/17/17 – 11/17/17 Traffic in the outside lanes.
Traffic impacts:
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is an alternative detour route signed for other traffic to bypass the project.
- Hill Avenue is now closed. Please use Elm Avenue as the alternate route.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Concrete Curb and Gutter
- East End – Birch Avenue to Hill Avenue
- Mainline water main and storm sewer
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Concrete Sidewalk
- East End – Birch Avenue to Hill Avenue
- Water Main Services and Storm Sewer
Next Contractors Meeting
Monday, July 10th, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level)
For additional information about the project, please visit the project website:http://projects.511wi.gov/ belknap/