Next Contractors Meeting

Monday, July 24, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
* South Side Construction       4/11/17 – 7/13/17    Bidirectional on the north side.
* North Side Construction       7/14/17 – 9/1/17     Bidirectional on the south side.
* Median Construction           9/5/17 – 10/6/17     Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End)                          Traffic Control
* South Side Construction       4/17/17 – 8/18/17     Bidirectional on the north side.
* North Side Construction       8/19/17 – 10/16/17    Bidirectional on the south side.
* Median Construction           10/17/17 – 11/17/17   Traffic in the outside lanes.

Traffic impacts:

  • Hill Avenue is now closed. Please use Elm Avenue as the alternate route.
  • Oakes is closed during this stage.
  • North Banks Avenue will be closed starting Monday 7/31/17.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Traffic switched to south lanes.
  • East End – Birch Avenue to Hill Avenue
    • Mainline Storm Sewer

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • North side removals
  • East End – Birch Avenue to Hill Avenue
    • Side Road Storm Sewer
    • Concrete Paving
    • Concrete Curb & Gutter
    • Concrete Sidewalk

Next Contractors Meeting

Monday, July 24th, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/