Next Contractors Meeting
Monday, July 30th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)
Traffic impacts:
- USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
- Signed truck detour and alternate route available to bypass project.
- Current Side Street Closures
- North Side
- Baxter Avenue
- Weeks Avenue
- Fisher Avenue
- Catlin Avenue
- South Side
- John Avenue
- Hughitt Avenue
- Cumming Avenue
- Hammond Avenue
- Baxter Avenue
- Clough Avenue
- North Side
Work completed since last update:
- South Side (John Avenue to Grand Avenue)
- Asphalt Pavement on side streets
- North Side (Weeks Avenue to Catlin Avenue)
- Gravel Base
- Light Pole Bases
Anticipated work schedule for next week:
- South Side (John Avenue to Grand Avenue)
- Asphalt Paving Side Streets
- Concrete Curb and Gutter
- Concrete Sidewalk
- Street Lighting
- UW-Superior signs
- Concrete Columns and Walls
- Landscaping
- North Side
- Concrete Removals – Grand Avenue to Weeks Avenue
- Concrete Paving – Weeks Avenue to Catlin Avenue
For additional information about the project, please visit the project website: http://projects.511wi.gov/