Next Contractors Meeting
Monday, July 16th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)
Traffic impacts:
- USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
- Signed truck detour and alternate route available to bypass project.
- Current Side Street Closures
- North Side
- Weeks Avenue
- Fisher Avenue
- Catlin Avenue
- South Side
- Clough Avenue South
- Baxter Avenue South
- Cumming Avenue South
- Hammond Avenue South
- Hughitt Avenue South
- John Avenue South
- North Side
Work completed since last update:
- South Side (John Avenue to Grand Avenue)
- Grading Hughitt Avenue to John Avenue
- Base Aggregate Hughitt to John Avenue
- North Side (Weeks Avenue to Catlin Avenue)
- Pavement Removal
- Curb and Gutter Removal
- Sidewalk Removal
Anticipated work schedule for next week:
- South Side (John Avenue to Grand Avenue)
- Paving Side Streets
- Concrete Paving Hammond Avenue to John Avenue
- Continue to work on Traffic Signals and Street Lighting
- Continue work on the UW-Superior signs
- Continue work on columns and walls
- Landscaping
- North Side (Weeks Avenue to Catlin Avenue)
- Water Services
- Storm Sewer
For additional information about the project, please visit the project website:http://projects.511wi.gov/