Next Contractors Meeting
Monday, June 19, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
South Side Construction       4/11/17 – 7/10/17     Bidirectional on the north side.
North Side Construction       7/11/17 – 9/1/17        Bidirectional on the south side.
Median Construction             9/5/17 – 10/6/17      Traffic in the outside lanes.

Birch Avenue to Hill Avenue (East End)                          Traffic Control
South Side Construction       4/17/17 – 7/30/17     Bidirectional on the north side.
North Side Construction       8/1/17 – 10/16/17     Bidirectional on the south side.
Median Construction            10/17/17 – 11/17/17   Traffic in the outside lanes.

Traffic impacts:

  • 6 Day Belknap Shutdown – Catlin Avenue to Hill Avenue
    • Belknap will be shut down from 6:00 am Saturday 6/24/17 until 6:00 am Friday 6/30/17 to complete water main and storm sewer installations.
    • Catlin Avenue will remain open during this closure.
    • Hill Avenue will remain open until 6/28/17. At this time, traffic should utilize Elm Avenue.
    • Access to all businesses will be maintained during the shutdown.
    • There will be a three day notice for any interruption to water service.
  • Fourth of July Holiday Weekend
    • The contractor will not be working on the project from noon Friday 6/30/17 until 6:00 am 7/5/17.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is also an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Mainline concrete pavement
  • East End – Birch Avenue to Hill Avenue
    • Water main

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Concrete Sidewalk
    • Concrete Curb and Gutter
  • East End – Birch Avenue to Hill Avenue
    • Storm Sewer

 

 

Next Contractors Meeting

Monday, June 19th, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/