Next Contractors Meeting
Monday, July 2nd, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)
Traffic impacts:
- USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
- Signed truck detour and alternate route available to bypass project.
- Current Side Street Closures
- North Side
- Catlin Avenue
- Weeks Avenue
- South Side
- Clough Avenue South
- Baxter Avenue South
- Cumming Avenue South
- Hammond Avenue South
- Hughitt Avenue South
- John Avenue South
- North Side
- There will be no work on the project from noon Tuesday 7/3/18 to 6:00 am on Thursday 7/5/18 for the observance of Independence Day.
Work completed since last update:
- South Side Water Main
- Storm Sewer to Hughitt Avenue
- Grading Lamborn Avenue to Cumming Avenue
- Concrete Sidewalk to Cumming Avenue
- East end traffic switch
Anticipated work schedule for next week:
- South Side (John Avenue to Grand Avenue)
- Finish Storm Sewer
- Grading Cumming Avenue to Hughitt Avenue
- Concrete Sidewalk
- Continue to work on Traffic Signals and Street Lighting
- Continue work on the UW-Superior signs
- Continue work on columns and walls
- Landscaping
- North Side (Grand Avenue to Catlin Avenue)
For additional information about the project, please visit the project website:http://projects.511wi.gov/