Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
South Side Construction 4/11/17 – 6/25/17 Bidirectional on the north side.
North Side Construction 6/26/17 – 8/23/17 Bidirectional on the south side.
Median Construction 8/24/17 – 10/6/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
South Side Construction 4/17/17 – 7/25/17 Bidirectional on the north side.
North Side Construction 7/26/17 – 10/3/17 Bidirectional on the south side.
Median Construction 10/4/17 – 11/17/17 Traffic in the outside lanes for
Traffic impacts:
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is also an alternative detour route signed for other traffic to bypass the project.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Water main complete from Banks Avenue to Ogden Avenue.
- Light bases complete at Banks Avenue.
- East End – Birch Avenue to Hill Avenue
- Pavement removals completed.
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Storm sewer installation
- Grading and gravel placement
- Light bases at Ogden Avenue
- East End – Birch Avenue to Hill Avenue
- Water Main
- Storm Sewer