Project Staging, Schedule and Traffic Overview:

Banks Avenue to John Avenue (West End)                    Traffic Control
South Side Construction       4/11/17 – 6/25/17    Bidirectional on the north side.
North Side Construction       6/26/17 – 8/23/17    Bidirectional on the south side.
Median Construction           8/24/17 – 10/6/17    Traffic in the outside lanes.

Birch Avenue to Hill Avenue (East End)                         Traffic Control
South Side Construction       4/17/17 – 7/25/17    Bidirectional on the north side.
North Side Construction       7/26/17 – 10/3/17    Bidirectional on the south side.
Median Construction            10/4/17 – 11/17/17   Traffic in the outside lanes for

Traffic impacts:

  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is also an alternative detour route signed for other traffic to bypass the project.

 

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Water main complete from Banks Avenue to Ogden Avenue.
    • Light bases complete at Banks Avenue.
  • East End – Birch Avenue to Hill Avenue
    • Pavement removals completed.

 

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Storm sewer installation
    • Grading and gravel placement
    • Light bases at Ogden Avenue
  • East End – Birch Avenue to Hill Avenue
    • Water Main
    • Storm Sewer