Next Contractors Meeting

Monday, May 22, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)              Traffic Control
South Side Construction       4/11/17 – 6/15/17       Bidirectional on the north side.
North Side Construction        6/16/17 – 8/14/17     Bidirectional on the south side.
Median Construction              8/15/17 – 9/27/17     Traffic in the outside lanes.

Birch Avenue to Hill Avenue (East End)                   Traffic Control
South Side Construction       4/17/17 – 7/17/17        Bidirectional on the north side.
North Side Construction        7/18/17 – 9/24/17     Bidirectional on the south side.
Median Construction              9/25/17 – 11/14/17    Traffic in the outside lanes

Project DetoursThere is a signed truck detour utilizing the City of Superior Truck Route. There is also an alternative detour route signed for other traffic to bypass the project. 

Traffic impacts:

  • Belknap will be closed between Tower and Banks for water main installation from 6:00 am Saturday 5/13/17 to 7:00 am Monday 5/15/17. Tower and Banks will remain open.
  • Belknap will be closed between Ogden and Tower for water main installation from 6:00 am Saturday 5/20/17 to 7:00 am Monday 5/22/17. Tower will remain open.
  • Night patching of Belknap will continue for the next couple of nights. Expect delays.
  • Ogden Avenue:
    • South of Belknap closed until 6/15/17.
    • North of Belknap closed until 8/14/17.
  • Bidirectional traffic on the east side of Tower Avenue (STH 35) from North 14th Street to North 16th Street.
Work completed since last update:
  • Banks Avenue removals and street lighting bases and signal bases.
  • Water main from Tower to Banks.
  • Hill Avenue Sediment Basin completed.
Anticipated work schedule for next week:
  • Continue water main and storm sewer work.
  • Continue with street lighting bases and signal bases.


Next Contractors Meeting

Monday, May 22nd, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website: http://projects.511wi.gov/belknap/