Next Contractors Meeting
Monday, May 22, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
South Side Construction 4/11/17 – 6/15/17 Bidirectional on the north side.
North Side Construction 6/16/17 – 8/14/17 Bidirectional on the south side.
Median Construction 8/15/17 – 9/27/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
South Side Construction 4/17/17 – 7/17/17 Bidirectional on the north side.
North Side Construction 7/18/17 – 9/24/17 Bidirectional on the south side.
Median Construction 9/25/17 – 11/14/17 Traffic in the outside lanes
Project Detours – There is a signed truck detour utilizing the City of Superior Truck Route. There is also an alternative detour route signed for other traffic to bypass the project.
Traffic impacts:
- Belknap will be closed between Tower and Banks for water main installation from 6:00 am Saturday 5/13/17 to 7:00 am Monday 5/15/17. Tower and Banks will remain open.
- Belknap will be closed between Ogden and Tower for water main installation from 6:00 am Saturday 5/20/17 to 7:00 am Monday 5/22/17. Tower will remain open.
- Night patching of Belknap will continue for the next couple of nights. Expect delays.
- Ogden Avenue:
- South of Belknap closed until 6/15/17.
- North of Belknap closed until 8/14/17.
- Bidirectional traffic on the east side of Tower Avenue (STH 35) from North 14th Street to North 16th Street.
- Banks Avenue removals and street lighting bases and signal bases.
- Water main from Tower to Banks.
- Hill Avenue Sediment Basin completed.
- Continue water main and storm sewer work.
- Continue with street lighting bases and signal bases.
Next Contractors Meeting
Monday, May 22nd, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level)