Next Contractors Meeting

Monday, May 14th, 1:00 pm at the Superior BID Office (823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Hill Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.
  • The project will keep 2 of these 3 side streets open for the duration of the project.
    • Catlin Avenue
    • Grand Avenue
    • Hammond Avenue
  • Current Side Street Closures
    • Catlin Avenue South
    • Clough Avenue South
    • Baxter Avenue South
  • Side Street Closures Scheduled For Next Week
    • Cumming Avenue South

Work completed since last update:

  • Pavement Removal – Catlin Avenue to Hammond Avenue
  • Temporary Signals

Anticipated work schedule for next week:

  • Pavement Removals – Hammond Avenue to Cumming Avenue
  • Continue with water main installation at Catlin Avenue moving west.
  • Begin storm sewer installation at Catlin working west.

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/