Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
South Side Construction – 4/11/17 – 6/15/17 Bidirectional on the north side.
North Side Construction – 6/16/17 – 8/14/17 Bidirectional on the south side.
Median Construction – 8/15/17 – 9/27/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
South Side Construction 4/17/17 – 7/17/17 Bidirectional on the north side.
North Side Construction 7/18/17 – 9/24/17 Bidirectional on the south side.
Median Construction 9/25/17 – 11/14/17 Traffic in the outside lanes.
Project Detours – There is a signed truck detour utilizing the City of Superior Truck Route. There is also an alternative detour route signed for other traffic to bypass the project.
Traffic impacts:
- Expect delays when travelling through the project.
- When approaching the project limits, Changeable Message Boards read:
- USH 2 Follow Detour
- Belknap Open For Business
- Ogden Avenue:
- South of Belknap closed until 6/15/17.
- North of Belknap closed until 8/14/17.
- Bidirectional traffic on the east side of Tower Avenue (STH 35) from North 14th Street to North 16th Street.
- Bidirectional traffic on the north side of Belknap from Birch Avenue to Hill Avenue.
- Left & Right turns onto Belknap are not allowed from Tower Avenue.
Work completed since last update:
- Recent rains cost the project a few days of work.
- Concrete saw cutting from Birch to Hill.
- Banks Avenue removals to start street lighting bases and signal base
Anticipated work schedule for next week:
- Asphalt saw cuts on side streets and parking lots.
- Begin decorative column and fence installations.
- Continue water main and storm sewer work.
- Continue with street lighting bases and signal bases.
Next Contractors Meeting
Monday, May 8th, 1:00 pm in the Lake Superior Room at the WIS-DOT Office at 1701 N. 4th Street.
For additional information about the project, please visit the project website: http://projects.511wi.gov/belknap/
Sincerely,
Brendan Dirkes, P. E. Project Manager Wisconsin Department of Transportation 715 395-3026 |
Pete Dieckman, P.E. Construction Project Leader Northern Wisconsin-Based Engineers, Inc. Belknap Field Office: 715 718-2334 |
Sign up for WIS DOT weekly construction updates here.