Next Contractors Meeting
Monday, April 30th, 1:00 pm at the Superior BID Office (823 Belknap Street, Ste. L-10)
Traffic impact:
- USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to John Avenue.
- Signed truck detour and alternate route available to bypass project.
- The project will keep 2 of these 3 side streets open for the duration of the project.
- Catlin Avenue
- Grand Avenue
- Hammond Avenue
- Current Side Street Closures
- Catlin Avenue South
- Clough Avenue South
- Side Street Closures Scheduled For Next Week
- Baxter Avenue South
- Cumming Avenue South
Work completed since last update:
- Pavement Removal – Catlin Avenue to Grand Avenue
Anticipated work schedule for next week:
- Pavement Removals – Grand Avenue to Hammond Avenue
- Begin water main installation at Catlin Avenue moving west.
For additional information about the project, please visit the project website: http://projects.511wi.gov/