Next Contractors Meeting
Tuesday, March 13th, 1:00 pm at the Wisconsin Department of Transportation Office
(1701 N. 4th Street)
Schedule: March 19, 2018 to October 3, 2018
Traffic impacts: None at this time.
Work completed since last update:
- 2017 Work Completed
- Banks Avenue to John Avenue
- Catlin Avenue to Hill Avenue
Anticipated work schedule for next week:
- Begin installation of temporary signals at Hammond, Grand and Catlin Avenues.
Anticipated work schedule for week of 3/19/18:
- Continue with work on temporary signals.
- Begin detour and alternative route signing.
- Begin saw cuts on the project utilizing flaggers.
For additional information about the project, please visit the project website:http://projects.511wi.gov/ belknap/