Monday, October 30, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
Miscellaneous Construction 8/29/17 – 10/27/17 Traffic on the inside lanes to allow work from the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
North Side Construction 8/24/17 – 10/20/17 Bidirectional on the south side.
Miscellaneous Construction 10/20/17 – 11/17/17 Traffic on the inside lanes to allow work from the outside lanes.
Traffic impacts:
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is an alternative detour route signed for other traffic to bypass the project.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Tower Avenue median
- Street Lighting
- East End – Birch Avenue to Hill Avenue
- Curb & Gutter
- Street Lighting
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Landscaping
- East End – Birch Avenue to Hill Avenue
- Driveway and Parking Lot Asphalt Pavement
- Landscaping
- Permanent Signing
- Pavement Marking
Next Contractors Meeting
Monday, October 30, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level)