Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
Miscellaneous Construction    8/29/17 – 10/27/17   Traffic on the inside lanes to allow work from the outside lanes.
                              
Birch Avenue to Hill Avenue (East End)                          Traffic Control
North Side Construction        8/24/17 – 10/20/17   Bidirectional on the south side.
Miscellaneous Construction    10/20/17 – 11/17/17  Traffic on the inside lanes to allow work from the outside lanes.

Traffic impacts:

  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Tower Avenue median
    • Street Lighting
  • East End – Birch Avenue to Hill Avenue
    • Curb & Gutter
    • Street Lighting

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Landscaping
  • East End – Birch Avenue to Hill Avenue
    • Driveway and Parking Lot Asphalt Pavement
    • Landscaping
    • Permanent Signing
    • Pavement Marking