Next Contractors Meeting
Monday, September 11, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
Miscellaneous Construction    8/29/17 –    Traffic on the inside lanes to allow work from the outside lanes.
                              
Birch Avenue to Hill Avenue (East End)                          Traffic Control
North Side Construction        8/24/17 –    Bidirectional on the south side.
Median Construction            10/16/17 – 11/17/17  Traffic in the outside lanes.

NO TURNING ONTO BELKNAP FROM TOWER!!! Superior Police Department has been monitoring the intersection. Please obey all construction signs to avoid backups. Thank You.

Traffic impacts:

  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Traffic Switch
  • East End – Birch Avenue to Hill Avenue
    • Pavement and Sidewalk Removals

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Concrete Sidewalk
    • Landscaping
    • Light Pole Placement
  • East End – Birch Avenue to Hill Avenue
    • Water main
    • Storm Sewer
    • Grading and Gravel
    • Concrete Pavement

Next Contractors Meeting

Monday, September 11, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/