Next Contractors Meeting

Monday, November 5th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.

Current Side Street Closures:

  • North Side
  • Weeks Avenue
  • Cumming Avenue
  • Hughitt Avenue
  • John Avenue

Work completed since last update:

  • Pavement Marking
  • Curb and Gutter
  • Traffic Signals
  • Signing

Anticipated work schedule for next week:

  • South Side
  • Finish work on the UW-Superior signs
  • Landscaping
  • Asphalt Parking Lots
  • North Side
  • Concrete Sidewalk
  • Asphalt Parking Lots
  • Landscaping
  • Finish work on the Douglas County Sign

For additional information about the project, please visit the project website: http://projects.511wi.gov/belknap/