Next Contractors Meeting

Monday, July 30th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.
  • Current Side Street Closures
    • North Side
      • Baxter Avenue
      • Weeks Avenue
      • Fisher Avenue
      • Catlin Avenue
    • South Side
      • John Avenue
      • Hughitt Avenue
      • Cumming Avenue
      • Hammond Avenue
      • Baxter Avenue
      • Clough Avenue

Work completed since last update:

  • South Side (John Avenue to Grand Avenue)
    • Asphalt Pavement on side streets
  • North Side (Weeks Avenue to Catlin Avenue)
    • Gravel Base
    • Light Pole Bases

Anticipated work schedule for next week:

  • South Side (John Avenue to Grand Avenue)
    • Asphalt Paving Side Streets
    • Concrete Curb and Gutter
    • Concrete Sidewalk
    • Street Lighting
    • UW-Superior signs
    • Concrete Columns and Walls
    • Landscaping
  • North Side
    • Concrete Removals – Grand Avenue to Weeks Avenue
    • Concrete Paving – Weeks Avenue to Catlin Avenue

For additional information about the project, please visit the project website: http://projects.511wi.gov/belknap/