Next Contractors Meeting

Monday, July 2nd, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.
  • Current Side Street Closures
    • North Side
      • Catlin Avenue
      • Weeks Avenue
    • South Side
      • Clough Avenue South
      • Baxter Avenue South
      • Cumming Avenue South
      • Hammond Avenue South
      • Hughitt Avenue South
      • John Avenue South
  • There will be no work on the project from noon Tuesday 7/3/18 to 6:00 am on Thursday 7/5/18 for the observance of Independence Day.

Work completed since last update:

  • South Side Water Main
  • Storm Sewer to Hughitt Avenue
  • Grading Lamborn Avenue to Cumming Avenue
  • Concrete Sidewalk to Cumming Avenue
  • East end traffic switch

Anticipated work schedule for next week:

  • South Side (John Avenue to Grand Avenue)
    • Finish Storm Sewer
    • Grading Cumming Avenue to Hughitt Avenue
    • Concrete Sidewalk
    • Continue to work on Traffic Signals and Street Lighting
    • Continue work on the UW-Superior signs
    • Continue work on columns and walls
    • Landscaping
  • North Side (Grand Avenue to Catlin Avenue)
    • Concrete Pavement Saw Cutting
    • Sign Removal

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/