Next Contractors Meeting

Monday, June 4th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Hill Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.
  • The project will keep 2 of these 3 side streets open for the duration of the project.
    • Catlin Avenue
    • Grand Avenue
    • Hammond Avenue
  • Current Side Street Closures
    • Fisher Avenue South
    • Clough Avenue South
    • Lamborn/Grand South
    • Baxter Avenue South
    • Cumming Avenue South
    • Hughitt Avenue South

Work completed since last update:

  • Water Main complete to Cummings Avenue
  • Storm Sewer complete to Baxter Avenue.
  • Grading mainline:  Fisher Avenue to Clough Avenue
  • Concrete Pavement: Catlin Avenue to Fisher Avenue
  • Curb & Gutter: Catlin Avenue to Fisher Avenue
  • UW Superior Foundations
  • Pavement Removal – Cumming Avenue to Hughitt Avenue

Anticipated work schedule for next week:

  • Pavement Removals: Hughitt Avenue – John Avenue
  • Continue with water main installation
  • Continue with storm sewer installation
  • Concrete Sidewalk: Catlin Avenue – Fisher Avenue

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/