Next Contractors Meeting

Monday, September 25, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                       Traffic Control
Miscellaneous Construction    8/29/17 – 10/20/17   Traffic on the inside lanes to allow work from the outside lanes.
                              
Birch Avenue to Hill Avenue (East End)                            Traffic Control
North Side Construction        8/24/17 – 10/16/17   Bidirectional on the south side.
Median Construction             10/16/17 – 11/17/17  Traffic in the outside lanes.

  • Traffic impacts:
  • PLEASE NOTE: We’ve recently discovered a conflict with an existing fiber optic line and the new light pole bases on the north side of the project from Catlin to Hill. We are moving the fiber optic line a few feet north to allow the light base installations. This work requires an open trench that will restrict access over the next few days. We appreciate your patience and all accesses will be restored next week.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Concrete Sidewalk
  • East End – Birch Avenue to Hill Avenue
    • Water Main
    • Removals

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Landscaping
    • Light Pole Placement
  • East End – Birch Avenue to Hill Avenue
    • Grading and Gravel
    • Concrete Pavement
    • Landscaping

Next Contractors Meeting

Monday, September 25, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/