Next Contractors Meeting

Monday, August 21, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
* South Side Construction        4/11/17 – 7/13/17     Bidirectional on the north side.
*  North Side Construction        7/14/17 – 9/1/17      Bidirectional on the south side.
*  Median Construction              9/5/17 – 10/6/17      Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End)                          Traffic Control
* South Side Construction       4/17/17 – 8/24/17     Bidirectional on the north side.
* North Side Construction        8/25/17 – 10/16/17   Bidirectional on the south side.
* Median Construction              10/17/17 – 11/17/17 Traffic in the outside lanes.

NO TURNING ONTO BELKNAP FROM TOWER!!!!! Superior Police Department has been monitoring the intersection. Please obey all construction signs to avoid backups. Thank You.

Traffic impacts:

  • Hill Avenue south is now open. Elm Avenue south is now closed.
  • Oakes Avenue is closed during this stage.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Concrete Pavement
  • East End – Birch Avenue to Hill Avenue
    • Curb and Gutter

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Concrete Curb and Gutter
    • Concrete Sidewalk
    • Concrete Light Bases
  • East End – Birch Avenue to Hill Avenue
    • Concrete Curb & Gutter
    • Concrete Sidewalk