Banks Avenue to John Avenue (West End)                      Traffic Control
* South Side Construction       4/11/17 – 7/13/17     Bidirectional on the north side.
* North Side Construction       7/14/17 – 9/1/17      Bidirectional on the south side.
* Median Construction             9/5/17 – 10/6/17     Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End)                          Traffic Control
* South Side Construction       4/17/17 – 8/24/17    Bidirectional on the north side.
* North Side Construction      8/25/17 – 10/16/17   Bidirectional on the south side.
* Median Construction            10/17/17 – 11/17/17  Traffic in the outside lanes.

NO TURNING ONTO BELKNAP FROM TOWER!!!!!!!!!! Superior Police Department has been monitoring the intersection. Please obey all construction signs to avoid backups. Thank You.

Traffic impacts:

  • Hill Avenue will be opening soon and Elm Avenue will be closed.
  • Oakes Avenue is closed during this stage.
  • North Banks Avenue is currently closed.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Traffic switched to south lanes.
  • East End – Birch Avenue to Hill Avenue
    • Mainline concrete pavement Hill to railroad tracks

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • North side removals
    • Concrete bases for street lights and signal bases
    • Grading
  • East End – Birch Avenue to Hill Avenue
    • Concrete Paving – Railroad tracks to Catlin Avenue
    • Concrete Curb & Gutter
    • Concrete Sidewalk