Next Contractors Meeting
Monday, July 10, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
South Side Construction 4/11/17 – 7/10/17 Bidirectional on the north side.
North Side Construction 7/11/17 – 9/1/17 Bidirectional on the south side.
Median Construction 9/5/17 – 10/6/17 Traffic in the outside lanes.
Banks Avenue to John Avenue (West End) Traffic Control
South Side Construction 4/11/17 – 7/10/17 Bidirectional on the north side.
North Side Construction 7/11/17 – 9/1/17 Bidirectional on the south side.
Median Construction 9/5/17 – 10/6/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
South Side Construction 4/17/17 – 7/30/17 Bidirectional on the north side.
North Side Construction 8/1/17 – 10/16/17 Bidirectional on the south side.
Median Construction 10/17/17 – 11/17/17 Traffic in the outside lanes.
6 Day Belknap Shutdown – Catlin Avenue to Hill Avenue
- Belknap will be shut down from 6:00 am Saturday 6/24/17 until 6:00 am Friday 6/30/17 to complete water main and storm sewer installations.
- Side roads in this section will be closed at the alleys.
- Access to all businesses and residences will be maintained during the shutdown.
- Catlin Avenue will remain open during this closure.
- Hill Avenue will remain open until 6/28/17. At that time, traffic should utilize Elm Avenue.
- There will be a three day notice for any interruption to water service.
Traffic impacts:
- Fourth of July Holiday Weekend
- There will be no work on the project from noon Friday 6/30/17 until 6:00 am 7/5/17.
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is an alternative detour route signed for other traffic to bypass the project.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Concrete Curb and Gutter
- East End – Birch Avenue to Hill Avenue
- Water main
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Concrete Sidewalk
- East End – Birch Avenue to Hill Avenue
- Water Main and Storm Sewer
Next Contractors Meeting
Monday, July 10th, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level)
For additional information about the project, please visit the project website:http://projects.511wi.gov/ belknap/