Next Contractors Meeting
Monday, June 19, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level)
Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
South Side Construction 4/11/17 – 6/25/17 Bidirectional on the north side.
North Side Construction 6/26/17 – 8/23/17 Bidirectional on the south side.
Median Construction 8/24/17 – 10/6/17 Traffic in the outside lanes.
Birch Avenue to Hill Avenue (East End) Traffic Control
South Side Construction 4/17/17 – 7/25/17 Bidirectional on the north side.
North Side Construction 7/26/17 – 10/3/17 Bidirectional on the south side.
Median Construction 10/4/17 – 11/17/17 Traffic in the outside lanes
- 6 Day Belknap Shutdown – Catlin Avenue to Hill Avenue
- Belknap will be shut down from 6:00 amSaturday 6/24/17 until 6:00 amFriday 6/30/17 to complete water main and storm sewer installations.
- Catlin Avenue and Hill Avenue will remain open during this closure.
- Fourth of July Holiday Weekend
- The contractor will not be working on the project from noon on Friday 6/30/17 until 6:00 am 7/5/17.
- Project Detours
- There is a signed truck detour utilizing the City of Superior Truck Route.
- There is also an alternative detour route signed for other traffic to bypass the project.
Work completed since last update:
- West End – Banks Avenue to John Avenue
- Storm sewer installation
- Grading and gravel placement
- East End – Birch Avenue to Hill Avenue
- Pavement removals completed.
Anticipated work schedule for next week:
- West End – Banks Avenue to John Avenue
- Concrete Pavement
- Concrete Curb and Gutter
- East End – Birch Avenue to Hill Avenue
- Water Main and Storm Sewer continue.
For additional information about the project, please visit the project website:http://projects.511wi.gov/