Water main installation on Belknap Avenue near the Elm Street intersection.

Next Contractors Meeting

Monday, June 19, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
South Side Construction       4/11/17 – 6/25/17     Bidirectional on the north side.
North Side Construction       6/26/17 – 8/23/17    Bidirectional on the south side.
Median Construction           8/24/17 – 10/6/17    Traffic in the outside lanes.

Birch Avenue to Hill Avenue (East End)                          Traffic Control
South Side Construction       4/17/17 – 7/25/17     Bidirectional on the north side.
North Side Construction       7/26/17 – 10/3/17   Bidirectional on the south side.
Median Construction           10/4/17 – 11/17/17   Traffic in the outside lanes


Traffic impacts:

  • 6 Day Belknap Shutdown – Catlin Avenue to Hill Avenue
    • Belknap will be shut down from 6:00 amSaturday 6/24/17 until 6:00 amFriday 6/30/17 to complete water main and storm sewer installations.
    • Catlin Avenue and Hill Avenue will remain open during this closure.
  • Fourth of July Holiday Weekend
    • The contractor will not be working on the project from noon on Friday 6/30/17 until 6:00 am 7/5/17.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is also an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Storm sewer installation
    • Grading and gravel placement
  • East End – Birch Avenue to Hill Avenue
    • Pavement removals completed.

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Concrete Pavement
    • Concrete Curb and Gutter
  • East End – Birch Avenue to Hill Avenue
    • Water Main and Storm Sewer continue.

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/