Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End) Traffic Control
South Side 4/11/17 – 6/15/17 Bidirectional on the north side.
North Side 6/16/17 – 8/14/17 Bidirectional on the south side.
Median 8/15/17 – 9/27/17 Traffic in the outside lanes for median work.
Birch Avenue to Hill Avenue (East End) Traffic Control
South Side 4/17/17 – 7/17/17 Bidirectional on the north side.
North Side 7/18/17 – 9/24/17 Bidirectional on the south side.
Median 9/25/17 – 11/14/17 Traffic in the outside lanes for median work.
Project Detour
Detour routes are currently signed as an alternate route and for truck traffic.
Traffic impacts:
- Currently:
- When approaching the project limits, Changeable Message Boards read:
- USH 2 Follow Detour
- Belknap Open For Business
- Ogden Avenue south of Belknap closed until 6/15/17.
- Ogden Avenue north of Belknap closed until 8/14/17.
- When approaching the project limits, Changeable Message Boards read:
- Bidirectional traffic on the east side of Tower Avenue (STH 35) from North 14th Street to North 16th Street.
- Bidirectional traffic on the north side of Belknap from Birch Avenue to Hill Avenue.
- The Week of April 20th – Hill Avenue remains closed north of Belknap for the construction of the Hill Avenue Storm Water Basin. Timing and length of closure weather dependent.
- Pavement removed from Banks to Ogden.
- Continue to construct Hill Avenue Storm Water Basin.
- Begin water main and storm sewer work.
Next Contractors Meeting
Monday, April 24th, 1:00 pm in the Lake Superior Room at the WIS-DOT Office at 1701 N. 4th Street.
Brendan Dirkes, P. E. Project Manager Wisconsin Department of Transportation 715 395-3026 |
Pete Dieckman, P.E. Construction Project Leader Northern Wisconsin-Based Engineers, Inc. Belknap Field Office: 715 718-2334 |